BED Electrical Line Changes

Attached are the preliminary plans for rerouting the electrical lines along Appletree Point Road.

Along the paved road, from 327 to the dirt road, the plan is to place the existing overhead line underground. This should be a fairly straightforward process, as much of the infrastructure to do so already exists.

Along the dirt road, some of the line will be put underground when the ditches are dug for the new sewer lines. The rest of the area will get new overhead lines, and some replacement poles.

These are preliminary plans, and may change considerably.  I will pass along further updates as they become available.